Construction Law in Saudi Arabia
Saudi Arabia’s legal system is based on the principles of Sharia Law which, following the literal interpretation of the teachings of the Qur’an.
The way in which
Saudi courts regulate contractual relationships is therefore extremely
different from the common and civil law systems. Parties are of
course free to contract with each other; however, the degree of freedom with
which they can do so is governed by certain prohibitions in the Qur’an. Generally
speaking, contractual provisions that violate the fundamental principles of
Sharia law will not be enforced by the Saudi courts.
There is no
construction law in Saudi Arabia, therefore all construction agreements in the
private sector are subject to the parties’ consent, provided that the agreement
does not contradict Sharia Law. However, there are some specific rules
that apply to public sector contracts pursuant to the Government Tenders and
Procurement Law 2006 (“the Procurement Law”) issued by Saudi Arabia Royal
Decree No. M58/1427, which was introduced to promote transparency, honesty,
economic efficiency and competition in the Kingdom.
A brief snapshot
of some of the key issues facing contractors in Saudi Arabia is set out
below.
Contracts and regulations
- For
public works contracts, the Saudi Arabian government uses its own standard
form of contracts. Public works contracts are subject to the provisions of
the Procurement Law.
- For
private contracts, the standard form of contract tends to be the same for
both local and international contractors. FIDIC contracts are widely
used throughout the region.
- Any
contractor designing or building in Saudi Arabia must abide by the Saudi
Building Code, which is a set of technical, legal and administrative
regulations regarding the minimum construction standards.
Duty of good faith
- The
principles of Sharia Law place great importance on the duty of good
faith. Whether a party has acted in good or bad faith will
depend on the particular facts and circumstances of each case.
- One
such example is a breach of the duty to warn. If the contractor was
aware of an error or defect but continued work without informing the
employer or the engineer they are likely to have acted contrary to the
duty of good faith.
Limitation/time bars
- In
common and civil law jurisdictions, if a claim is time-barred this will
provide the defendant with a very strong defence. However, there is
no statutory limitation period in Saudi Arabia. Saudi courts
will uphold contractual limitation periods if they accord with Sharia Law
principles.
- For
example, Saudi courts may refuse to dismiss a claim on the basis of a
limitation argument in circumstances where (i) it would be unfair to the
claimant, and (ii) rights should not be lost with the passage of time,
both of which would contravene the principles of Sharia
Law. Allegations of fraud and bad faith are not subject to
limitation periods.
Remedies for breach of
contract
Sharia law
prohibits riba (unjust enrichment) and gharar (speculation).
Therefore contractual remedies are limited to direct and actual damages
suffered and damages cannot be claimed for indirect or consequential losses,
loss of business, loss of profit, economic loss of a chance or any other type
of speculative or uncertain losses. Similarly, specific performance and
injunctive relief are generally unavailable.
Delay, disruption and
acceleration
- Article
52 of the Procurement Law permits extensions of time if the contract is
extended because: (i) the employer requests additional works; (ii) the
annual budget allocated to the works is insufficient for completion by the
original completion date, and (iii) the relevant public authority suspends
the works through no fault of the contractor.
- A
disruption claim will only be successful if the loss suffered was direct,
fair and proportionate, and that the contractor took reasonable steps to
mitigate the losses. As set out above, Sharia Law prohibits
unjust enrichment and speculation, therefore a contractor may only recover
damages for the amount of loss actually incurred.
Liquidated damages
- Liquidated
damages clauses are generally permitted but are subject to the principles
of Sharia Law set out above. Therefore they will only be
enforceable to the extent that the amount of delay damages accurately
reflects the actual damages incurred.
- In
relation to public sector contracts, Articles 48 and 49 of the Procurement
Law stipulate that delay penalties should be subject to 10% liability cap
for all tenders and procurements undertaken by government entities and a
6% cap for supply contracts.
Termination
- For
public works contracts, the government has the right to terminate the
contract in certain circumstances, as set out in Article 53 of the
Procurement Law. The circumstances include (i) bankruptcy of
the contractor; (ii) assignment or subcontracting the contract without
permission of the government; (iii) the contractor’s failure to rectify
delay or breach of contract within 15 days of the government’s notice to
do so, and (iv) if the contractor commits bribery. Article 54
entitles a contractor to damages if the government authority terminates
the contract with no valid grounds.
- The
Saudi courts will generally uphold the termination provisions for private
contracts. The courts will also permit termination for reasons
not stipulated in the contract if there are valid grounds.
Force majeure
- Force
majeure provisions are recognised in Saudi law; however, the courts will
only recognise exceptional events beyond a party’s control that make
performance absolutely impossible rather than overly burdensome.
- However,
for public sector contracts Article 51 of the Procurement Law provides
that a contract will be extended (and the penalty waived) if the delay is
due to unforeseen circumstances or reasons beyond the contractor’s
control.
Variations
In relation to
public works contracts, variations are permitted under Article 36 of the
Procurement Law. An increase in the scope of work is permitted up to
10% of the contract value whereas omissions are capped at
20%. In relation to private contracts, the courts will
generally uphold the provisions of the contract provided that they do not
violate the principles of Sharia Law.
Completion of the works
- There
are no specific rules governing completion of the works save for (i)
Article 53 of the Procurement Law which confirms that in relation to
public projects, the government has the right to withdraw work from a
contractor and rescind the contract or execute it at its own cost if the
contractor abandons the project without completing, and (ii) Article 40 of
the Procurement Law which provides that the last payment (not less than
10% for public sector contracts and 5% for private sector contracts)
should be paid after the initial handover of the works.
Dispute resolution
- Construction
disputes can be heard by the Sharia Court, the Board for the Settlement of
Commercial Disputes, the Board of Grievances and the Labour Courts.
- In the
private sector, parties are free to litigate or arbitrate (pursuant to an
arbitration agreement) in accordance with the terms of the
contract. As per Article 11 of the New Arbitration Law 2012,
parties are bound by their agreement to arbitrate but can also bring
parallel proceedings in the Saudi courts if there are issues of Sharia Law
that must be resolved. It is worth noting that domestic arbitration is
governed by the Board of Grievances and can therefore be just as costly
and time consuming as litigation. Mediation is typically only
used where mandatory under statutory requirements.
- In the
public sector, an ad hoc committee will be formed to hear disputes
concerning (i) an alleged breach of contract by the government body; (ii)
an alleged breach of contract by the contractor; (iii) defective
performance by the contractor, and (iv) fraud, deceit or manipulation, but
only on the part of the contractor. Either party can appeal the
committee’s ruling to the Board of Grievances within 60 days of the
decision.
Bankruptcy/insolvency
- Bankruptcy
or insolvency of the contractor is grounds for termination in a government
contract pursuant to Article 53(d) of the Procurement Law.
- In relation
to the private sector, the parties are free to include termination
provisions in the contract in the event of bankruptcy or
insolvency. There is no provision in Saudi law that
automatically treats a contract as void or voidable in those
circumstances.
Comments
Post a Comment